Click any numbered step to view its RAMS / WPS / QI docs (from Prod. doc. mapping (as-is) ). Add new items, edit names & URLs, drag-and-drop files anywhere in a section to attach them, and use Preview to inspect. Files and edits are stored in this browser - use Export edits to share with teammates.
1.1 Delivery of Plates/Flange
1.2 Inspection of Plates
1.3 Inspection of topflange,
MP/TP Flange
1.5 Inspection of secondary
items at CSWO
2.1 Plate joining
Welding longitudinal Seam
2.2 Rolling Can Tack Welding
2.3 In and Out Plates Welding Longitudinal Seam
2.5 Final NDT of Longitudinal Seam
2.8 (Can 1) Mounting/tack
welding EWP Support ring
2.9 (Can 1)
Welding EWP Support Ring in
Horizontal Position
2.13 Assembly Section 1
2.14 Circular Welding Inside
2.16 Internal flange
measurement
(After assembly)
2.18 (Can 6) Mounting and
Tack weld Seafastening
Flange
2.19 (Can 6) Welding
Seafastening Flange
1. Incoming Control
2. Black Steel (Section 1)
Can 1,2,3
2. Black Steel (Section 2)
Can 4,5,6
2.22 Assembly Section 2
3. Assembly
Sec.1+Sec.2
3.1 Final Assembly of TP
Tack welding
3.2 Circular Welding inside
Flanges first, and final weldings
second.
3.3 Circular Seam Milling
outside
3.4 Circular Welding Outside
3.5 Grinding Round seam
3.6 NDT for Circular Welding
4. Hole/Mounting
Secondary Steel
4.1 Holes for Cable transit
Ventilation pipe,
Pressure relief holes,
ICCP outlet hole.
4.2 Drilling and making thread
for HDPE guides
4.3 Final Measurement in
Workshop, internal Flange
Measurement, Seafastening
flange
4.4 Mounting and welding
ICCP system+cable tray,
Installation guides,
Anode support Stubs
4.5 Mounting and welding
Cable pipe supports.
4.7 Black Steel Inspection
Before mounting
4.8 Mounting and welding
Rest platform Stubs,
Upper ladder supports.
4.9 Mounting and welding
Rest platform/Boat landing/
Cable pipe,
Final Secondary steel.
4.10 Black Steel inspection
After mounting
5. Painting (TP)
5.2 Inspection of
Steel Surface
5.1 Blasting
5.4 Coating
6.5 Airtight Platform
5.1 Blasting
5.4 Coating
6.5A Mounting Airtight seal
6.5B Mouting membrane,
Supports, closing hatches
Etc.
6. Upending
6.1 Internal Horizontal
Check
6.7B Load Test of Davit Crane
6.3 Mounting
HDPE Guides.
6.4 Upending
6.5 Mounting Airtight
Platform
6.6 Mounting internal
Platforms, UWP + JBP
6.7 Mounting External
Platform
6.8 Flange
Measurement
6.9 Final Mounting
6.12 Check of loose items
6.6C Preliminary Test on
completion
6.6D Factory Acceptance
Test: Internal Inspection +
rectification of punches.
7.4 FAT Closure
with client + employer
7.5 Harbour Acceptance Test
7.6 Loadout
6.6 Internal PlatformS,
UWP + JBP
6.6A Assembly Internal
Platforms, UWP + JBP
6.6B Electrical Outfitting
Internal platforms, UWP + JBP
6.7 External Platform
6.7A Mounting Railing
Equipment and grating
5.1 Blasting
5.4 Coating
Process flow Chart _Project Nordlicht
1-
TP Aalborg –
ON 311301 (TP
’
s)
Doc.: QF
-311301-10.54-999-999-27-
UKDate: 09
-
04
-202
6 Revision: 7
2.4 Calibrating Can in Rolling Machine
2.10 NDT for EWP Support Ring
2.20 NDT for Seafastening
Flange
Witness
Hold
Hall 20
Tent 109
Tent 126
Tent 110
Hall 2
Hall 1
Hall 21
Sterke Workshop 6
Upending area
4.6 Mounting of 2 support
beams for external working
platform
5.3 Re-Blasting
2.23 Circular Welding Inside
2.11 Drill the hole for EWP
Support Ring in Vertical Position
Tent 109
2.7 (Can 1) Mounting Top
Flange Tack Welding
Hall 22
2.15 Mounting
MP/TP flange tack welding
Hall 22
Hall 22
7.3 FAT Inspection
Hall 1
7.1 Internal Test On Completion
(Weight if any)
Tent 108
Hall 24
Hall 25, 6, 15
7. Handover and
delivery
7.2 FAI - Only for TP-01
: Vertical
: Horizontal
2.6 Turn in Vertical Position
2.12 Turn in Horizontal Position
2.17 Turn in Vertical Position
2.21 Turn in Horizontal Position
Hall 14
6.11 Electrical Testing
6.10 Electrical Outfitting
6.5C Electrical Outfitting on
ATP
6.7C Electrical outfitting on
EWP.